I plan to start work at 7AM on the 29th. We'll need a work train so we can load tools, joint bars, bolts, spikes, rail saw, rail drill, etc., to take with us. The work train will go ahead of 51 and the load of rails and wait for us at the tie pile hear MP 7. We will load ties on top of the load of rail (this is an experiment that Jason wants to try and if it is workable it will change the way we approach track laying in the future) and then proceed to TOM to lay the first 150 feet of the mill siding.