Author Topic: October 2015 Work Planning  (Read 64245 times)

James Patten

  • Administrator
  • Superintendent
  • *****
  • Posts: 4,486
  • Loco for 6
    • View Profile
October 2015 Work Planning
« on: September 30, 2015, 06:02:49 AM »
Anticipated work for weekend of October 3 & 4.  As this is the weekend before the work weekend, volunteers will probably be a little scarce.

* Car barn: finish the roof?  Check out Mike's ditches and do what we can inside to get ready for the track laying.
* Loco 9
* Run trains.

Jason M Lamontagne

  • Operating Volunteers
  • Supervisor
  • ******
  • Posts: 1,877
    • View Profile
Re: October 2015 Work Planning
« Reply #1 on: September 30, 2015, 07:42:20 PM »
There is a charter Sunday afternoon.  Volunteers for hosting, and some remaining train crew needs, would be extremely helpful.

Jason

Dwight Winkley

  • Museum Member
  • Fireman
  • ****
  • Posts: 373
    • View Profile
Re: October 2015 Work Planning
« Reply #2 on: October 02, 2015, 04:57:52 PM »
After viewing photo's of the carbarn it looks like one or two more rows of 2" X 6" purlin's need to added to the sides of the car barn, up near the roof before the siding can be installed. Can't see if the ends need purlins do to the staging.
dwight
« Last Edit: October 02, 2015, 08:34:04 PM by Dwight Winkley »

Stewart "Start" Rhine

  • Museum Member
  • Superintendent
  • ********
  • Posts: 3,034
    • View Profile
Re: October 2015 Work Planning
« Reply #3 on: October 02, 2015, 06:29:02 PM »
Dwight,

We have the lumber to put purlins in the gables, most 2X4's are on the pipe staging at the south end.  There's a bit of fancy cutting to fit the purlins in the trusses, we just need time and people to install them.

Paul Uhland

  • Museum Member
  • Dispatcher
  • *****
  • Posts: 1,074
    • View Profile
Re: October 2015 Work Planning
« Reply #4 on: October 03, 2015, 12:24:35 AM »
Looks like bracing and sheathing at the gable ends will require custom cutting.
That's how it is.
Paul Uhland

Stewart "Start" Rhine

  • Museum Member
  • Superintendent
  • ********
  • Posts: 3,034
    • View Profile
Re: October 2015 Work Planning
« Reply #5 on: October 03, 2015, 06:00:24 AM »
It's the same type of purlins we put on the garage.   

James Patten

  • Administrator
  • Superintendent
  • *****
  • Posts: 4,486
  • Loco for 6
    • View Profile
Re: October 2015 Work Planning
« Reply #6 on: October 03, 2015, 05:15:33 PM »
Work done Saturday Oct 3 2015:

* Car barn - the roof is on!  There's still some trimwork to do, but the big job is over.  The side staging was taken down soon after.  In the late afternoon Mike cut a ditch across where the track will go and put in a small culvert.
* Landscaping - Mike put in a big culvert across where the woods track will go, to drain the pond on the west side of the car barn.  It was pretty muddy, the dozer looks like it's been mud running.
* Loco 9 - Marcel assembled one of the cab walls and brought it and the rear corner posts into the machine shop for priming and painting later.  He plans to work on the other tonight or tomorrow.

Mike Fox

  • Museum Member
  • Empire Builder
  • ********
  • Posts: 5,914
    • View Profile
Re: October 2015 Work Planning
« Reply #7 on: October 03, 2015, 07:19:40 PM »
Actually Brendan did the digging this afternoon, I was clean up and mive the tractor guy.



The ditch before the culvert went in.









Drain pipe across under tracks
« Last Edit: October 03, 2015, 07:34:34 PM by Mike Fox »
Mike
Doing way too much to list...

Fred L. Kuhns

  • Museum Member
  • Hostler
  • ***
  • Posts: 224
    • View Profile
Re: October 2015 Work Planning
« Reply #8 on: October 03, 2015, 10:01:04 PM »
Mike thanks for posting the pictures of the work on Car Barn and drainage. Can see how the water will be removed from the west side of the Car Barn. Brendan and the Deere did a very nice job. I know the roofing crew is glad to see the last of the metal installed.   Thanks Fred L. Kuhns

Paul Uhland

  • Museum Member
  • Dispatcher
  • *****
  • Posts: 1,074
    • View Profile
Re: October 2015 Work Planning
« Reply #9 on: October 04, 2015, 01:02:55 AM »
Great pics. You guys are really the Seabees NE civilian branch, right?  ;)
Amazing that you all 'git-er-done' when necessary.
Nice to know the roof is complete, standing water is gone, a drainage system now exists, sheathing can soon start.
Looks like lots of expected track ballast rock was dumped east of the CB.
Good thing your JD tractor handles a backhoe. Am praying for Kubota's recovery and hi-rail conversion.
Paul Uhland

Mike Fox

  • Museum Member
  • Empire Builder
  • ********
  • Posts: 5,914
    • View Profile
Re: October 2015 Work Planning
« Reply #10 on: October 04, 2015, 07:56:49 AM »
Actually pulled the Kubota off the dead line for a little bit, just to get the culvert work done. Put on a good smoke show with it.
Mike
Doing way too much to list...

Paul Uhland

  • Museum Member
  • Dispatcher
  • *****
  • Posts: 1,074
    • View Profile
Re: October 2015 Work Planning
« Reply #11 on: October 04, 2015, 11:42:13 AM »
See? Now the Kubota is also a 'mosquito fogger'.  ;D
What a country.
Paul Uhland

Tom Casper

  • Museum Member
  • Hostler
  • ***
  • Posts: 216
    • View Profile
    • Sandy Ridge & Clear Lake Ry.
Re: October 2015 Work Planning
« Reply #12 on: October 05, 2015, 10:01:29 AM »
See? Now the Kubota is also a 'mosquito fogger'.  ;D

LOL LIKE

Tom C.
Later:
tom_srclry_com

James Patten

  • Administrator
  • Superintendent
  • *****
  • Posts: 4,486
  • Loco for 6
    • View Profile
Re: October 2015 Work Planning
« Reply #13 on: October 07, 2015, 06:02:50 AM »
Anticipated work for weekend of October 9 - 12: Fall Work Weekend!

* Track laying: Construction of two switches and laying of track into the car barn (or out of the car barn to the switches - depending on how it all works out!).  Ballasting of same (the stone supply is right next to the car barn) and doing whatever we have to do to make it serviceable.  And if we have time, constructing some of the Woods Track.
* Car barn: Siding and upper purlins.  Personally I'd like to be building track inside the barn before the siding goes up so that we have more light.
* Food: Kitchen crew will be busy.
* Loco 9: Perhaps cab assembly and tank placement.  Once either/both are on, plumbing. 
* Passenger trains: Last weekend for steam and for Sunday operations.
* Track maintenance: If there's time and crew.

There's a board meeting on Friday evening.  It will be somewhere on campus!

Mike Fox

  • Museum Member
  • Empire Builder
  • ********
  • Posts: 5,914
    • View Profile
Re: October 2015 Work Planning
« Reply #14 on: October 07, 2015, 06:59:44 AM »
I thought the tank was going out to get the coal bunker coated before installation
Mike
Doing way too much to list...