Work done on Saturday September 26:
* Car barn: The east side roofing is now done. Zack worked on plywood on the door end (as a stiffener). Meanwhile Mike used the dozer to remove dirt from the sides of the barn outside (both sides), then removed the piled up dirt underneath the walls. He also sprinkled dirt in some low places inside.
* Fall Festival: We had a good amount of visitors. We brought the caboose up on the first trip and left it on the siding at AC. Later in the day we needed a handicap accessible car, so we put a flatcar on the end and kept it on the train all day.