Work done on Saturday August 29:
* Car barn: Yesterday Brendan dug for the east door post footing, which was placed and buried. Today Mike dug for the west door post footing. There was concern that we would encounter the effluent pipes for the septic system, however we did not find them. Concrete for both footings were poured today. Before the footings were poured, some more roofing went up on the west side, yesterday and today.
* Loco 9: Marcel continues to work on the cab. Sand blasting continues with the tank.
* Landscaping: The bulldozer got fixed, and Mike pushed some dirt around for the car barn switch and tracks.