Hey Everyone,
The rail we'll be laying during the Work Weekend is scheduled to arrive this week so we'll need as many hands as possible on Saturday 9/13 to move it to the rail pile at the end of track. We also have ties to move. If we get the rail done in a timely fashion we could start moving ties. We also have ten foot ties on the way (delievery next week?) which will need to be cut in half, treated on the cut ends, moved, etc. So, I 'm sure there will be another day dedicated to tie work prior to the work weekend. We have enough ties on hand for about 900 feet of track which means we'll need 150 more to lay all the rail.