Work completed Tuesday and Wednesday 1-2 August 2023
Tuesday:
* Track crew completes the required stone work under the north side of Trout Brook Bridge.
(Steve Lx, Brian W, Paul R, Ellen, Tyshawn, Joe D, James P)
* Locomotive #9 rebuilding the rear buffer beam continues. (Eric, Harold)
* Coach #9 assembly. Prep for varnishing continues (Lou)
* Passenger car truck rebuild, design corrections being made (Jerry, Carlos, Jason)
* Rail car Training (Pete S., Ben R, Jason)
* Trout Brook Bridge pest control, equipment repair (Bill Baskerville)
* Alna Center mowing. (Randy)
* Sheepscot Yard maintenance and repair. (Jay Barta)
* Engine house build continues. (Stewart, Fred, Brendan)
* Archive work continues (Linda)
* Gift shop/mail continues (Cindy R)
Wednesday:
* Locomotive #9 Buffer beam work continues (Eric, Jason, Roger and Wes C)
* Engine House build continues. (Brendan, Stewart)
* Equipment repairs and SS yard maintenance continues. (Jay Barta)
* Admin work. (Steve P)
* Archives work continues (Linda)
* Polling stock oil/greasing (Phil B)
* Off site work on various truck parts (Randy)
Notes: Bob Longo in for schedule work… noted work canceled.
Megan on leave from the Coast Guard, visits and helps Track crew with stone work.
A lot of work going on this week.