Work completed Tuesday and Wednesday 18-19 January 2022.
Tuesday:
* Shop work, vacuum brakes continued with new parts being machined. (Jonathan)
* Track work, Trask and MLMW crossings salted. (Steve L, JB Smith)
* Propane tank refill and shop lighting. (Brendan, Fred)
Wednesday:
* Shop work, fabrication of parts continues. (Jonathan)
* Vehicle repair on Casey continues. (Mike)
* Yard switching, Loco #7 moved to Shop bay #2 temporarily. (Steve L, Chuck, Dan, Brendan, Mike)
* Track work, Janesway and Brook Crossings ice removal, partially open. (Steve L, Dan, Chuck)
Note: The heavy rain and freezing temps from the last storm has presented the railroad with a of ice .
Clean will be continual and on going.
Just to point out the Gift Shop/mail work happens just about every day and handled by Cindy R.