If we are able to raise the money to get the large washout/avalanche stabilized, there should be plenty of main line track work to do.
First we need to grade the Clark and Fossell property in 2009 or 2010. This gives us two years of additional main track laying.(2010-2011)
Then we need to stabilize the washout and grade to the next washout(2011-2012) and this gets one more year main track laying. (2012)
Then we need to replace two washouts with culverts and grade to the brook (2012) this gets us to the Carleton Brook Bridge (Trout) one more years tracklaying (2013)
Then Carleton Brook bridge must be built (2012-2013), and we can lay track to Rte 218.
Based on our past experience, this is a very doable, leisurely schedule.
But it is going to take a lot of money and volunteer effort.