Been a while since I've posted on the weekday effort but I mean to do so more regularly. So here's an attempt!
Yesterday, Monday, Nov 2, Jonathan finished making connections from the tank to the injectors. Last week he finished the vacuum brake plumbing- this all major plumbing on no 9 is complete. Some of it has been removed for paint access. Brendan continues work on interior tank braces.
Today Josh is up to essentially complete no 9 electrical. Tuesday Phil (Bleauvelt) will likely finish the steam line to the generator, while I'll make some slight mods to the frame casting to clear a washout plug and then work on vacuum brake and generator exhaust lines.
Tomorrow, Wednesday, we'll switch the yards out, do some minor inspection work at the bridge and make a repair to a ToM switch. Starting Wednesday we're going back to very limited access inside the tent so Stewart and Marcel can work on finish application of wood cab components, paint, and varnish, without worrying about us marking up the paint job mid way through.
Thursday will likely see some coach brake mods as we give the paint crew space... We'll also begin on a new plow mounting arrangement for 52 soon.
No 9 is nearing a test fire, as you may have guessed. It won't be this month- as it looks now...
See ya
Jason