Work done on March 1 & 2:
* #9: Friday, Jason and Jonathon worked on T-Bolts for the wheel binders. They didn't finish. Saturday, Eric S continued working on something related to that. Saturday afternoon Brendan showed up and started working on something, probably the tank.
* Crane car: Mike was busy, first replacing the temporary chain from which the top hangs with a permanent chain, then working on braces to keep the rail clamps from kicking out.
* Plowing: Steve, Stewart, Fred, Mike and I plowed out the main line, as far as Sheepscot Mills (which had logging activity). Brook Crossing was especially bad with ice, two inches or more over the rail.