Work done on weekend of September 18,
* Fred, Dwight, and possibly others continued working on brush cutting, working on Cock-eye Curve.
* John M did some phone line repair
* Mike, myself, and Bill F. jacked and tamped about 45 feet on the mainline south of the water tank. Thank goodness Mike was around because we had some air hose issues. Now it needs stone but the ties are solid (and the track is level!). Later Mike got some supplies and did some work on Big Joe's air hoses.
* Got my first operational trip on the railcar, along with a few others.
* Jason started some work on 9's frame, mainly filing to receive the casting. The casting was moved from Cincinnati milling machine to the shaper next to it.
* Zack brought in the floor plan for the restroom, and a location was staked out.
* Sunday was a birthday party in the caboose. Earlier in the week, Steve Z built a fence for the caboose doors.