The grade from end of track to the bridge needs to be graded to get the old ties and stumps out, rebuild the ditch on the East side and put in rip rap rock and fill as needed. That work will begin once the permit dates are effective again as the wetland permit we have is only good 3 months per year for two years. This being the second year on the permit.
For the Fall Work Weekend our goal is to build 2,000' of track. Which will require 150 rails, 300 joint bars, 1,000 ties, 4,000 spikes, and 600 bolts and washers to be readied ahead of time.