Author Topic: Mountain Extension - Official Work Thread  (Read 536130 times)

Fred Morse

  • Museum Member
  • Engineer
  • ****
  • Posts: 642
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #615 on: June 27, 2018, 04:47:52 PM »
We've been chipping away at the pine pile at the North end this week. Three pickup truck loads taken over to Johnny. About 5 loads left.

Mike Fox

  • Museum Member
  • Empire Builder
  • ********
  • Posts: 5,642
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #616 on: June 27, 2018, 07:53:29 PM »
Very good Fred
Mike
Doing way too much to list...

Jeff Schumaker

  • Museum Member
  • Inspector
  • ******
  • Posts: 1,353
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #617 on: June 28, 2018, 09:03:05 AM »
Hopefully, all the loads will be gone by the time I come up in mid July. ::)

Jeff S.
Hey Rocky, watch me pull a moose trout out of my hat.

Dwight Winkley

  • Museum Member
  • Fireman
  • ****
  • Posts: 373
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #618 on: June 28, 2018, 09:31:20 AM »
Oh good, you can help pick up the old ties from the spring work weekend.

Mike Fox

  • Museum Member
  • Empire Builder
  • ********
  • Posts: 5,642
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #619 on: June 28, 2018, 08:29:14 PM »
Another permit was completed tonight, ready for the presidential stamp of approval this weekend, provided he is available..
This one is for the second large culvert we need to install. 4 feet tall, 40 feet long.. Hope to mail on Monday.
Mike
Doing way too much to list...

Dave Buczkowski

  • Museum Member
  • Conductor
  • *****
  • Posts: 981
  • Life Member
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #620 on: June 28, 2018, 10:22:31 PM »
Mike, I’ll stop in on Saturday to sign it.
Dave

Mike Fox

  • Museum Member
  • Empire Builder
  • ********
  • Posts: 5,642
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #621 on: June 30, 2018, 07:25:53 PM »
 Saturday morning I arrived to find contractor Jeff left 4 loads of the bony gravel..



After an hour..


Looking South from Location 15




Location 14, looking north toward 218



Mike
Doing way too much to list...

Brendan Barry

  • Museum Member
  • Dispatcher
  • *****
  • Posts: 1,067
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #622 on: June 30, 2018, 07:35:30 PM »
The contractor has also started work on filling in the slide at location 4 on the right of way down the mountain.

Excavator sitting on the right of way. The present end of track is about 50 ft behind the camera.



The slide area with new gravel going in place. The land slide area started right after the big pine tree on the left.

United Timber Bridge Workers, Local 1894, Alna, ME

Bill Baskerville

  • Museum Member
  • Inspector
  • ******
  • Posts: 1,417
  • Life Member
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #623 on: June 30, 2018, 09:24:21 PM »
Wow! massive earth works going on.  Real progress being made both on the ROW and on the bridge installation slide beams.
~ B2 ~ Wascally Wabbit & Gofer ~

Jeff Schumaker

  • Museum Member
  • Inspector
  • ******
  • Posts: 1,353
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #624 on: July 01, 2018, 09:04:44 AM »
Mike,

How much has been graded south from 218?

Jeff S.
Hey Rocky, watch me pull a moose trout out of my hat.

Wayne Laepple

  • Museum Member
  • Yardmaster
  • *******
  • Posts: 2,123
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #625 on: July 01, 2018, 09:50:56 AM »
How is the contractor compacting the new fill material at the slide location, and what is holding the bottom to keep it from moving again?

Mike Fox

  • Museum Member
  • Empire Builder
  • ********
  • Posts: 5,642
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #626 on: July 01, 2018, 12:47:31 PM »
Jeff, we have made it within 50 feet of the Alna Shoreland Zone permitted area. That starts in the cut. One more load will do it.

Our contractor is using the same method he did with the fill of the washout last year, which is more compaction than the original had. Proper drainage and keeping the trees off the slope will help keep this stable for a long time.
Mike
Doing way too much to list...

Wayne Laepple

  • Museum Member
  • Yardmaster
  • *******
  • Posts: 2,123
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #627 on: July 01, 2018, 01:06:28 PM »
Two more questions:

Is the new fill on the slide wider on top than the original was?

Is the fill material falling to its angle of repose?
« Last Edit: July 01, 2018, 01:08:47 PM by Wayne Laepple »

Jeff Schumaker

  • Museum Member
  • Inspector
  • ******
  • Posts: 1,353
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #628 on: July 01, 2018, 02:20:54 PM »
Jeff, we have made it within 50 feet of the Alna Shoreland Zone permitted area. That starts in the cut. One more load will do it.

Our contractor is using the same method he did with the fill of the washout last year, which is more compaction than the original had. Proper drainage and keeping the trees off the slope will help keep this stable for a long time.

Once that 50 ft is graded, what's next?

Jeff S.
Hey Rocky, watch me pull a moose trout out of my hat.

Mike Fox

  • Museum Member
  • Empire Builder
  • ********
  • Posts: 5,642
    • View Profile
Re: Mountain Extension - Official Work Thread
« Reply #629 on: July 01, 2018, 04:07:13 PM »

Once that 50 ft is graded, what's next?

Jeff S.

I go south. Contractor Jeff takes over.
Mike
Doing way too much to list...