Work completed Tuesday and Wednesday 11-12 July 2023
Tuesday:
* Track crew completes a long lift, ballast level and tamp between TOM and Fossil Crossing.
(Steve Lx, Brian W, Steve Lt, Paul R, Ellen R, Leon, Tyshon, Dan, Nick)
* Engine House insulation batten, flooding track with stone north side (Brendan, Fred, Stewart)
* Mowing, Weed Whacking AC, SS (Jay Barta, Randy)
* Coach #9 build, varnishing the clerestory frames. (Eric, Harold, lou, Ron)
* Locomotive #9 maintenance (Roger, Wes)
* Locomotive #9 rear end beam replacement (Eric, Randy)
* Archives work continues (Linda)
* Gift shop/mail on going daily (Cindy R)
* Admin work (Ed)
Wednesday:
* Coach #9 build continues with more varnishing (Eric, Ron, Harold, Seth)
* Engine house work continues (Brendan, Fred, Stewart)
* Locomotive #9, rear, end beam replacement. (Eric, Randy)
* Archives work (Linda)
* Track crew Lifts, ballasts, level 2 locations on TB main line. (Steve Lx, Brian W, Steve Lt, Leon)