Work completed on Tuesday and Wednesday 1-2 November 2022
Tuesday:
* Crews work on capping the engine house roof with plywood and then covered with ice/water shield.
(Brendan, Steve Lx, Steve Lt, Brian W, Jay Barta, Paul Richards, Randy, Leon, Fred)
* Passenger truck rebuild continues with priming and painting frames. (Jerry, Carlos)
* Coach #9 assembly continues with interior work. (Eric, Ron)
* Rail Car #4 work continued and builders get together. (Paul R, Leon, Brendan)
* Archive work continues (Linda)
Wednesday:
* Mountain grade survey conducted (Jonathan, Randy)
* Engine house and various projects. (Fred, Brendan)
* Locomotive #3 off loaded and in for repairs
Note: I was not at SS today so several projects/folks have been missed.