Work completed Tuesday and Wednesday 27-28 September 2022
Tuesday:
* Passenger trucks rebuild, the crew is stacking up welded truck frames. (Jerry and Carlos)
* Vacuum brakes design, test, build, parts are being made for more brake systems (Jonathan, Randy)
* Coach #9 assembly, build, interior trim continues (Eric, Ron, Harold, Lou)
* locomotive #9 State Inspection, (Roger, Bob Longo, Dan , Jason)
* Archives work continues (Linda)
* Gift shop/mail on going (Cindy R)
* Equipment repair, small motors, #52 sand boxes repair (Jay Barta)
* Engine house build on roof continues (Brendan, Fred, Steve Lx, Steve Lt)
* Admin (Dave B, Jason)
Wednesday:
* Vacuum brake parts being made continues (Jonathan, Randy, Mark)
* Gift shop/mail continues daily (Cindy R)
* Archive work continues (Linda)
* Coach #9 and Coach #3 work continues (Eric, Ron, Harold, Lou)
* Grease/oiling rolling stock (Phil B)
* Admin work (ED)
* Engine house roof work, the 1st covering of the roof is completed.
(Brendan, Fred, Steve Lx, Steve Lt, Mark)