Detailed 2022 FWW Track Work Plan
Friday:
Kink Repair (Steve Lennox, Jason), 1-2 helpers, including equipment to repair rail breaks.
Lining (Dana, Dan). In vicinity of kink repair. Majority of Friday track crew.
Saturday:
2 Lining Crews, both based out of Alna Center. Lunch at AC. PLEASE PARK AT AC!!!!
Crew 1 (Steve Lennox, Dan).
Crew 2 (Steve Leet, Mark Cheetham).
Both crews on foot out of AC, ideally 15-20 each crew. Lining bars for all. 2 flagmen per crew for train protection.
Sunday:
Tamping (Steve Lx), Harsco, 1-3 helpers.
Ballast Dressing (Dana, Dan)
Monday:
Pit Rail Install (JML, Dana, Dan)