Work completed Tuesday and Wednesday 30-31 August 2022
Tuesday:
* Track crew preps materials for crib placement, material and tool inventory,
(Steve Lx, Brian W, Steve Lt, Leon, Jared, Mark, Scott)
* Shop crews Vacuum brakes test end with successful test, waiting for parts to continued work
(Jonathan, Randy)
Passenger truck build continues, noting crew was bending the truck frames for mounting
(Jerry, Carlos)
* TBS Build continued (Brendan, Fred)
* Coach #9 assembly and build continues (Eric, Ron, Lou)
* Campus clean up/dump run (Stewart R)
* Gift shop/mail on going (Cindy R)
* Archives work on going (Linda)
* SS station and admin work (Ben)
Wednesday:
* Track crew makes delivery of steel for axles to ML&MW received by Brian F., crew inspects TOM
work sites, ROW clean up including vegetation removal, ties set up and recovery of old ties,
short pipe sections unloading work flat and TBS construction flat.
(Steve Lx, Steve Lt, Paul R, Elijah)
* Shop work, Band saw cart work completed, equipment/material repairs (Jay Barta)
* SS campus mowing (Fred)
* Back Hoe repairs (Brendan)
* Coach #9 assembly and build work continues (Eric, Ron, Harold)
* SS clean up (Stewart)
* Rolling stock oil/greasing (Phil B)
* Archives work on going (Linda)