Work completed Tuesday and Wednesday 2-3 August 2022
Tuesday:
* Track crew completes ballasting,lifting,level and tamping TBS tail track
Switching equipment begins from TBS to TOM
(Steve Lx, Steve Lt, Brian W, Mark, Jay Barta, James P, Joseph,
* Shop crew continues work on Passenger car truck rebuild. (Carlos & Jerry)
Vacuum brake testing continues (Jonathan)
* Coach #9 build continues (Eric, Ron)
* Locomotive maintenance #7, #9 (Jason, Roger, Dan, Joseph
* Locomotive #11 work session (Rick, Gordon, Wayne L, John Kokas)
* TBS station build, (Fred, Zack Steve P, Stewart)
* TBS bridge maintenance/painting (Stewart)
* AC mowing (Randy)
* Archives (Linda)
* Gift shop/mail (Cindy R)
Wednesday:
* Track crew clean up and dressing track at TBS, all equipment moved to TOM completed
(Steve Lx, Steve Lt, Paul R, Elijah R, Leon, James P, Dave B, Dave Hempstead)
* Locomotive #11 work session continues, (Rick, Gordon, Wayne, John Kokas)
* Coach #9 build continues (Eric, Ron)
* Archives (Linda)
* Gift shop/mail (Cindy R)
* TBS build north wall siding completed (Fred, Zack, Steve P, Stewart)
* TB Bridge painting completed (Stewart)
* Locomotive #7 and #9, test run turning both locomotives on turn table
(#7 crew Jason, Roger, #9 crew Wes, Gordon, Conductor Dan, Brakeman Bill R, JB Smith,
Steve P, Steve Lx, Steve Lt, James P, )
* Rolling stock grease/oiling (Phil B)
* Communication checks (Joseph, John M)
Note: This was a busy two days for all hands. This included Dan and Bill R making up the test train and yard switching. A lot of stop ins from members and visitors alike