Work completed Tuesday and Wednesday 26-27 July 2022
Tuesday:
* Track crew lift level tamping TBS runaround track and TT leads. Prep for MP 8, spiking tail track
(Steve Lx, Steve Lt, Brian, Leon, Randy,)
* TBS station build, roof shingling started, (Brendan, Fred, Stewart)
* TBS turn table leveling continues, (Jason, Randy, Jay Barta)
* Passenger truck rebuild continues, (Jerry, Carlos)
* Coach #9 assembly/build continues (Eric, Ron, Harold, Lou)
* Archives work (Linda)
* Gift shop, mail (Cindy R)
* SS campus clean up, trash run (Stewart)
Wednesday:
* Track crew completes spiking tail track, assist with turntable test.
(Steve Lx, Brian W, Steve Lt, Paul, Elijah, Randy, Jay Barta, Jason)
* TBS station build, roof shingling completed, (Brendan, Fred, Stewart)
* TBS turntable work and test w/locomotive #9 (Jason, Randy Jay Barta, Mark C, Track Crew)
* Locomotive #9 boiler wash, fill and fire, turn table test, (Roger, Dan, JB)
* MP 8 signage completed (Eric)
* Archive work continues (Linda)
* Gift shop/mail continues (Cindy R)
NOTES: The turn table worked well with #9 on it, there are a great many events and projects being worked on off site. Project sites have regular visits from members like Zack W, Steve Z, and Dave B.
The railroad continues to be a busy place 7 days a week.