Work completed Tuesday and Wednesday 12-13 July 2022
Tuesday:
* Track crew continues lifting, leveling and tamping TBS track
(Steve Lx, Brian W, Steve Lt, JB, Joe Fox, Dan, Nick)
* TBS work: Station building roof rafters started (Brendan, Fred, Stewart)
Trail, ROW weed whacking (Randy)
Kiosk set up (Randy, Steve Lt, Brian W, Steve Lx, Dan)
Turn table work (Jason, Randy Jay Barta)
* Vacuum brakes design/build/test continues (Jonathan)
* Passenger truck rebuild continues (Carlos, Jerry)
* Coach #9 assembly/build continues (Eric, Ron, Lou)
Wednesday:
* Track crew continues lift, level, tamp TBS main track, jacks set for next week tamping
(Steve Lx, Steve Lt, Paul, Elijah, Chuck, Jason, Randy, Jay Barta)
* TBS build continues on roof rafters (Brendan, Stewart, Fred campus clean up and trash run (Ste)
* Coach #9 assembly, build continues (Eric, Ron)
* SS Campus clean up and trash run (Stewart)
* Gift shop on going weekly (Cindy R)
Notes: I’m sure I have missed someone or a project but work around the railroad is continual and busy