Work completed Tuesday and Wednesday 5-6 April 2022.
Tuesday:
* Track crew, Track started laying track at Trout Brook Station on the run a round
(Steve Lx, Steve Lt, Paul, Brian W, Eric, Randy, Leon, Jonathan, Joe Lupinsky, Dwight
Jason, Pete & Cody)
* Engine House, crew continues to move along, see up coming pic’s.
(Brendan, Fred Stewart)
* Gift shop/Mail on going daily. (Cindy R)
* Rolling stock lubrication/oiling. (Phil B)
* Admin (Bob Holms)
Wednesday:
* Track crew, Crew completes laying track to turn table on both run around and main line.
( Steve Lx, Steve Lt, Brian W, Paul, Leon, Eric, Randy, Jonathan, Joe Lupinsky, Dwight,
Jason, Dan)
* Engine house crew continues (Brendan, Fred, Stewart)
* Shop, Locomotive #11 work. (Gordon C)
* Campus clean up, dump run (Stewart)
Note: This was Pete and Cody’s first time working with the rail crane and laying track.
Cody worked in various positions from tie insta-track, to joint bar placement and bolting,
he put in a long day and did a good job.