Work completed Tuesday and Wednesday 11-12 January 2022
Tuesday:
* Shop work, Vacuum brakes design/build continued Jonathan)
Passenger truck rebuild continued (Jerry, Carlos
* Coach #9, Preparation for move to Bay 4, (Eric, Steve L, Brian, Chuck, Phil B)
* Track crew, Yard switching with freight consist made up, coach #20 returned to car barn,
Tampers relocated. (Brian W, Chuck, Steve L)
Wednesday:
* Coach #9, Final preparation, coach moved to shop bay #4.
(Eric, Chuck, Brian W, Brendan, Mike, Steve L)
First passenger… Fred
* Garage, Vehicle repair (Casey) (Mike)
* Campus clean up/dump run (Stewart)