Work completed Tuesday nd Wednesday 28-29 September 2021.
Tuesday:
* Track work, set up begins for the run through engine house switch
( Steve L, Steve Leet, Chuck, Paul, Scott, Randy, Stewart)
So. Switch cribbing at Alna Station repaired (Steve Leet)
* Shop, Passenger truck rebuild continues (Jerry, Carlos)
Locomotive #9, plumbing for the fireman's side injector starts (Josh, Jason, Johnathan)
Vacuum brakes, planner repair (Jonathan)
* Coach #9 assembly, (Eric, Ron, Lou)
seat castings (Harold)
* Engine House build continues, (Fred, Stewart, Lou, Randy Mark)
* Gift shop/mail (Cindy R)
* Campus clean up and trash run (Stewart)
Wednesday:
* Track work, switch build continues, points, frog and rails selected moved to ties
(Bryce, Chuck, Brian W, Steve Leet, Scott, Jason, Randy)
* Shop, Locomotive #9 gets the new injector and testing work to follow Jason, Johnathan, Bryce)
Vacuum brake work continues (Jonathan, new volunteer Dave)
* Coach #9 assembly continues, roof sheathing (Eric, Ron)
* Engine house build continues, (Fred, Stewart, Eric)
* Harsco Tamper work, clean up of several small machines (Jay B)
* Archives, (Linda)