Work completed Tuesday and Wednesday June 6-7 2021.
Tuesday:
* Fred Shed, work continues with new shelving and work benches. It is noted that Stewart and crew
have been working on the shed Saturday through Monday.
* Coach #3, wheel replacement, the truck was pulled, wheels replaced and truck remounted.
(Jason, Eric, Jerry, Randy, Elija, James)
* Coach #9 assembly continues. (Ron, Lou)
* Car journal oiling (Phil)
* Location #8 Crib, constructed (Steve L, Leon, Chuck, Brian W)
* Engine house work (Brendan)
* Box car rebuild (Marcel)
Wednesday:
* Ballast, Fred loaded ballast for crib work.
* Location #8 Crib, ballasted, clean up and completed (Steve L, Leon, Chuck)
* Coach #3 wheel replacement, truck adjustment, replacement completed. (Jason, Eric, Randy)
* Coach #9 assembly. (Eric, Ron)
* Locomotive Maintenance, #9 smoke box cleaned out, #8 steam cleaned (Bryce)
* Sheepscot Campus mowing. (Fred)
* Switching, Coach #3 returned to Car Bar bay #1, (Brendan, Steve L)