Work completed Tuesday and Wednesday 23-24 March 2021.
Tuesday:
* Tamper (Wilma) Function checks, equipment checks for repairs, relocated to the machine shop
bay #3 lead. (Steve L, Joe F, Brian W. Chuck B)
* Yard switching, included Open car, Caboose #554 moved to the Woods track, 1 Flat to the loading
ramp, 2 Flats and Tank car moved to Main Line.
* Fire Wood (Fred)
* Bridge work (ventilation- Randy)
* Sheepcot Campus clean up (everyone)
* Painting, Dairy Car and Machine shop windows (Stuart)
* Brookville moved from Machine shop Bay #3 to Bay #1) (pushed)
Wednesday:
* Sheepcot Campus clean up and firewood (Fred, Brendan, Chuck B, Steve L)
* Shop work (Jerry and Carlos)
* Yard Switching, Locomotive’s moved, #4 to loading ramp, #8 to run through lead.
This clears up the display tracks for Round House work. (yes, it looks pretty bare)
(Jason, Brendan, Steve L, Dan M, Randy)
* Loaded flat moved to ML&M. (Dan M, Steve L)