Since there was not a formal report for work completed on Saturday, 11/21:
* Sandy River Surprise!
#9, backdated to SR&RL #6 ran to ML&M to retrieve P&R Combine 2 and P&R Coach 4. Then operated 2 sold out ( <15 passengers per car) trains for photographers, families, and invited guests. Runbys occurred at Alna Center, Hummason Brook, and Sutters (1pm trip only). At the end of the day, the cars were spotted on the ramp track for loading. As dusk turned to night, P&R Coach 4 was loaded onto the ML&M flatbed with custom car length extender for the trip to Portland. See Facebook for (lots more) photos.
* Pavilion
Bracing is complete (or nearly so); roof assembly begins FRIDAY 11/27!
* B&SR 56
The siding is almost completely removed. Care is being taken to save as much material as possible. The tar-paper roof did a great job protecting much of the car's structure.
* Electrical Building
Shingling is complete on 3/4 of the building. The front needs the window installed before the shingling can be finished on that side.
* Other, but Equally Important
Gift shop was open and doing business.
Archives were hopping (with new volunteer Nicole helping Linda.)
Please add/correct as needed.