Work completed Tuesday July 21 and Wednesday July 22, 2020.
Tuesday:
* Track inspection from Alna Center to TOM.
45 joint bars tightened. One immediate rail joint repair needed.
* Coach #9 construction, frame assembly begins.
* Tie pick up and replacement along ROW, pick up stalled due to a wasp attack.
* Shop work, building #52 springs.
* Beginning of SS pick up and maintenance.
* Work on locomotive #9 pilot.
* Archive and Gift work Shop.
* Tamper maintenance
Wednesday:
* Crew to assemble locomotive #9 pilot.
* Crew working track to include completing rail joint repair, track lift
at Foster Rd. crossing. More ballast expected to complete the lift.
* Work on MNG locomotives (Catherine)
* Brake repair on coach #3
* Dump, campus maintenance.
Sorry if I have missed anything, 14 volunteers today.