Work done on Saturday June 27:

* Ballasting: we unloaded 6 flatcars of stone on The Mountain.  There's two more for early in the week left at the bottom of the hill to take care of the kink.  Zack estimates 12 more flatcar loads.  We had a crew of 11 in the morning.
* Loader: Brendan was working on the loader before we left in the morning, but I don't know the outcome.
* Paint: Stewart put another coat of paint on the MNG/B&SR tank car, and on the new car barn doors (which aren't yet hung).
« Last Edit: June 28, 2020, 05:03:02 PM by James Patten »

James Patten

  • Administrator
  • Superintendent
  • *****
  • Posts: 4,216
  • Loco for 6
    • View Profile
Re: June 2020 Work Reports
« Reply #31 on: July 01, 2020, 02:45:07 PM »
Work done on Monday, June 29:

* Ballasting and lining: the Monday crew ballasted north of the bridge on the first unballasted section.  Then lining occurred.  It's better than it was.

Bill Piche

  • Museum Member
  • Fireman
  • ****
  • Posts: 385
    • View Profile
Re: June 2020 Work Reports
« Reply #32 on: July 01, 2020, 07:10:01 PM »
All this rock going down is great, but just out of curiosity has the section around Fossel been attended (or will be) in all of this summer work?
Engineer/Fireman, MNGRR/WW&F/Essex
"Any day with steam is a good day." - me

Paul Uhland

  • Museum Member
  • Dispatcher
  • *****
  • Posts: 1,074
    • View Profile
Re: June 2020 Work Reports
« Reply #33 on: July 02, 2020, 10:44:50 AM »
If anybody's available, a trackwork pic or two would be wonderful.   
Hat's off to all  youz summertime gandies.

Car barn big door hanging progress?
Thanks.