Work done at Sheepscot 8/8/18
The four corners that the bridge sits on were bolted together. Took the day to complete, and may not seem like much, but they are 3 wood blocks, each one weighs around 300 lbs or more and to drill through all three the top block on each one had to be removed to finish drilling the last two. Then pounding the long bolts through was another chore in itself.
Piles were sorted and loaded at Sheepscot in preperation for the contractor.
Work went on at the bridge site to prep for the piles, including the contractor rigging the crane up for setting piles.
Grass was mowed at Alna Center to be ready for this weekend.
Sheepscot was a very busy place yesterday, and if something happened that was not mentioned its not intentional.