Boxcar 56 is in bay 3 and will remain until complete. Coach 9 has been in shop bay 2 and will move to bay 4 indefinitely. As they move into finer interior work, being near the wood working tools in bay 4 will be helpful.
9 and 10 will move into bay 2 for now, where some preparatory work will occur on no 10, and no 9 will be housed for the duration of February Steam & Sleighs operations. Bay 1 will host the rail car and locomotive 7.
Following S&S, loco 7 will be winterized and placed back in the car barn. 9 will move to bay 1, with the half bay in bay 2 available to get a start on loco 11’s frame, as well as permit the loco 10 project to spread out a little.
Once box 56 is done, 10 will likely move there- giving each 10 and 11 a full bay.
Once the enginehouse is complete, 9 and the rail car will move there, permitting bay 1 to be used for Wilmer and similar projects.
At least that’s the current outlook..
Thanks
Jason