Work done today, December 5:
I had to leave at 2:15 so I missed a few things later in the day.
* Car barn: the north wall is nearly finished if not fully. The third bay was done, the second bay was nearly done, and the first bay was being worked on. Scafolding was down over barn bay 3.
* 118: We cleaned off the car, putting the 25-lb rail between the Woods track and the barn bay 3 track.
* Bulldozer: Mike and I got the dozer this afternoon, and spotted it on the unloading track back at Sheepscot. It was coming off as I was leaving.
* Loco 9: Big news for it. Hydro test Thursday, steam test Friday at which they discovered a bunch of leaks that they addressed yesterday and today, and another steam test today. Before light-off the dome cover was put back on in Bay 1, then it was put by the woodpile and lit off. I think it had pressure by lunch, after lunch Jason and crew spent time getting the various parts and pieces working. Josh was working on getting wiring to the rear headlight, which was being mounted at the same time. The whistle was blown while Mike and I were up getting the dozer (heard it pretty clearly), then again for me before I left (I could feel it in my chest - sounds great!). After I left it moved on its own power. My wife and I showed up just as it was returning from Alna Center towing Coach 3 and full carload of people.