The bridge work outlook is fairly clear next week and gets hazy further out, due to weather and work progress uncertainty.
Week of July 9 (Next week):
Monday, Tuesday: pre-fab bridge abutments at Sheepscot.
Wednesday: install silt fence, mark out abutment excavation at bridge site (finish abutments if needed).
Mon-Wed: paint bridge (different crew). (Painting could happen this or next Saturday, as possible. Check with Linc- as the wood needs to be dry, and the work coordinated.)
Thursday: (rain forecast): continue work on steel temp spans.
Week of July 16.
Remove stumps from south bank.
Jeff excavates for north abutment
Prepare stone bed for north abutment
Install pre-fab abutment.
Jeff backfills abutment.
Week of July 23:
Prepare for and drove piles for bents.
At that point, while we have goals, it’s best to wait rather than announce plans. As we get closer we’ll post updates.
See ya
Jason