Work done on Saturday, June 6
* Whitefield Section House - Mike dug a ditch for the posts, placed the posts, and filled the ditch back in. This is getting ready for Steve P and Annie B's wedding in two weeks, which will feature a work weekend type atmosphere.
* Car barn - Several of us put in bracing, and started putting 2x4s up for the metal roof attachments. The trusses are still pretty wobbly. We ran out of ambition mid-afternoon. The roof attachments are about 2/3 done on the west side on the upper half of the roof.
* Loco 9 - Marcel was working on the cab. He's nearly done with the roof, starting to work on the side posts. On one of the posts he was trying to leach out old oil soaked in to the board by using Acetone (I think that's what it was). I've also heard that the cast iron sheets for the jackets has been shipped out to be cut, polished and treated.