I have this springs Track Work line up for the three days of work weekend.
Friday - tamp low spot(s) between TBS station and TBS switch and fix switch cross level and some stone for curve super elevation. End of Friday we should have the curve prepped for stone trains on Saturday.
Saturday - Big job south of TB Bridge. That will need a lot of stone run both before and after lifting. Saturday morning two stone trains (hopefully) to very thoughtfully pre-stone locations south and north of the bridge, wind rows of stone- using both hopper and flat. Then Saturday afternoon do the lifts south to north, running stone trains to dress what you’ve just lifted, again south to north.
Sunday - Finish dressing both south of TB Bridge and TB curve as necessary and general clean up, make sure we get the super elevation right, half day potentially.