Work done on Saturday June 13:
* Rock the Mountain: We had a good crew of 15 today. Apparently we were supposed to wait until 8:30 for depature (as mentioned in Facebook), which I didn't know about, and I hadn't set a departure time here. So we left early and left some people behind. Fortunately they found their way. We didn't put out as much rock this time around, as the weekday crew had jacked what we stoned the week before. We refilled in the jacked area, then continued on to new track. We did only one round of 4 cars in the morning.
* Rail replacement: Dana and Joe knew about a rail that needed to be replaced on the new track built last year, so they went to investigate. Final result was no rail replaced, but they know what they need.
* Culvert replacement: Although finished with the culvert, Mike still needed to get material to the repair site. We brought the tipcar up and left it for him at Sheepscot Mills. He used it to haul material to the work site to dump. He's done with that.
* Vehicle repair: The John Deere engine is apart looking for the solution to it quitting. Brendan and Mike started to take apart the Case loader wheels to replace the brakes (only the left side removed).
* #9 repair: Alan was working on repairing a part of 9 that broke when the pilot got caught.
* Board meeting: Started at 4, was broadcast online, ended 6:20ish.