Work done on Saturday Sept 9:
* Ties: Fred was eager to get the ties stacked at ToM, so a trainload of people went up to unload them. After the train returned to Sheepscot the car got loaded with more ties.
* Culvert work: The crane car has been removed from the site, and Mike started removing stumps from the north side in order to make it easier for Jeff Verney to get in to check out what needs to happen. Mike also dug in one of the two lower culverts.
* Car shop: A crew was busy installing electrical conduit where the floor will go.
* Measuring: for our 5-year site plan with the Town, part of the plan is a list of culverts. We have a log of culverts but I updated it, walking with the measuring wheel from MP 7 down to the end of track.
* Board meeting: long board meeting tonight, largely taken up by bridge talk.