Restroom construction progress on 9/8 and 9/13:
I have a couple of progress photos for the restroom building, hoping I can figure out how to post them.
When I went to Sheepscot Monday the 10, I took the first picture, showing the east side of the restroom building with the 19 roof trusses put up by the volunteers by 9AM on Saturday the 8th.
When I returned to Sheepscot Thursday the 13th, I took the second picture showing the plywood sheathing Zack Wylie and Steve Zuppa applied, covering the east side of the roof, on Wednesday the 12th.